Tullynamoyle Windfarm (Phase2)
Main Civils and Building Contractor for the construction of 20kv ESBN Substation and Windfarm Control Building as per ESBN specifications. Bulk excavation of peat on site . Excavation of floor slab area and laying of concrete slab. Wall construction of external cavity blocks and internal block walls. Placing of fire resistant foil backed plaster board […]
Main Civils and Building Contractor for the construction of 20kv ESBN Substation and Windfarm Control Building as per ESBN specifications. Bulk excavation of peat on site . Excavation of floor slab area and laying of concrete slab. Wall construction of external cavity blocks and internal block walls. Placing of fire resistant foil backed plaster board and plastering. Roof construction and completing site services installation.
Client: Tim Boland ( Tullynamoyle Windfarm)
Our Roll: Main Contractor and PSCS
Skills Needed:
General Construction
Project Management
Risk Management
Site Logistics